A pile splice joins two segments of a driven pile, using either a weld (typical for H beams), grout or mechanical means (typical for precast concrete piles). Pile splices enable the use of shorter segments, which allows for driving piles in low-headroom situations such as under bridges or inside buildings. Reducing length of pile segments to under ~65 feet long also means the trailers that haul them to job sites can stay within state length limits.桩接头连接打入桩的两段,使用焊接(典型的 H 梁)、灌浆或机械方法(典型的预制混凝土桩)。桩接头允许使用较短的部分,这允许在低净空情况下打桩,例如在桥下或建筑物内部。将桩段的长度减少到 65 英尺以下也意味着将它们拖到工作地点的拖车可以保持在常规长度限制内。 往期精彩合集点击