某国外露天铁矿日终简报如下:
Iron Ore Mine – Opencast Daily Production Report
Mine Name:ABC Iron Ore Mine
Location:—
Date:—
Shift Covered:A / B / C
Mining Method:Opencast (Shovel–Dumper)
Reporting Officer:—
1. Executive Summary(管理层一页摘要)
|
|
|
|
|
|
|
|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
总体状态:🟡产量略低于计划,主要受降雨及铁路发运延误影响;剥离任务完成良好。
2. Shift-wise Production Summary(三班工作量)
|
|
|
|
|
|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 合计 | 23,400 | 44,500 | 1.90 |
3. Pit & Bench-wise Production(矿点工作量)
|
|
|
|
|
|
|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Equipment Deployment & Performance(设备情况)
4.1 Shovel Performance(推土机)
|
|
|
|
|
|
|
|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.2 Dumper Performance(自卸卡车)
|
|
|
|
|
|
|
|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.3 Drilling & Blasting(钻爆)
|
|
|
|
|
|
|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5. Dispatch & Logistics(运输)
|
|
|
|
|
|
|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
| 合计 | 22,000 | 21,300 | 700 |
|
6. Quality Control(铁矿石品位)
|
|
|
|
|
|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7. Fuel & Energy Consumption(能耗)
|
|
|
|
|
|
|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8. Manpower Deployment(雇员情况)
|
|
|
|
|
|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 合计 | 193 | 188 |
|
9. Safety & Environment
(安全)
各班完成Toolbox Talk
无LTI / MTI / FA
速度监控正常
(环保)
洒水抑尘 ✔
排水沟 ✔
破碎站抑尘 ✔
噪音合规 ✔
10. Key Issues & Bottlenecks(其他情况)
B班降雨影响钻孔与运输效率
低RL平台混采导致品位稀释
铁路编组延误约4小时