In Thailand in March, the temperature in the factory reached 40℃. The high-temperature and high-humidity environment posed significant challenges for equipment installation and commissioning.
Mr Zhang, a senior engineer of PalletMach, led the team to efficiently promote every task and fulfill the delivery commitment with sweat.
Mr Zhang's installation timeline
March 12-13th (Days 2-3) -Efficiently completed the assembly of the plastic molding machine, strictly controlling the assembly accuracy.
March 14-15th (Days 4-5) -Completed the assembly of the first and second extruders and metering tank, precisely calibrated the parameters, ensuring the plasticization efficiency of raw materials and the quality of pallets.
(During equipment installation)
(The production was carried out smoothly using the customer's raw materials)
(Train the employees of the client)
It's Not Just Speed, But PalletMach's Delivery Strength
Completing the delivery in 15 days is not accidental. Throughout the whole process from equipment production, delivery to on-site installation and commissioning.
During the project, the Thai customer fully cooperated, worked hand in hand with PalletMach's team to jointly overcome many challenges, and achieved double savings in time and cost through two-way cooperation.
If you also have waste plastics, please scan the QR code to get in touch with us.